# How to estimate bath to shower conversion from scope to total in Australia Plan a bath to shower conversion quote for one existing bath alcove in Australia. Follow metric measurements, the Sydney, New South Wales worked calculation, scope boundaries and a matching AUD PDF. Canonical: https://quicklyestimates.com/en-au/guides/how-to-estimate-bathtub-to-shower-conversion/ Author: Estimates editorial team Published: 2026-09-25 Updated: 2026-09-25 For one existing bath alcove, start with a defined scope and measurement basis. Measure the finished alcove on three sides, the wet-wall area and the drain location before selecting the base. Keep the shower base, screen and finish tile as named allowances until the products are selected. Price the listed tasks separately and state the condition that would require a revision: Rot behind the surround or a drain that cannot align with the chosen base changes the work. The Sydney, New South Wales worked example checks 7 AUD cost lines and a A$7,194.83 fictional subtotal against the measured scope. Review the matching PDF before making your own quote. THE ESTIMATING ANSWER For one existing bath alcove, start with a defined scope and measurement basis. Measure the finished alcove on three sides, the wet-wall area and the drain location before selecting the base. Keep the shower base, screen and finish tile as named allowances until the products are selected. Price the listed tasks separately and state the condition that would require a revision: Rot behind the surround or a drain that cannot align with the chosen base changes the work. This guide follows one existing bath alcove in Sydney, New South Wales . The matching itemised estimate and PDF (https://quicklyestimates.com/en-au/samples/bathtub-to-shower-conversion-estimate/) show how the job brief becomes measured quantities and separate AUD amounts. The responsible role in this scenario is renovation contractor. Check the actual site, selected products, supplier figures and labour plan before issuing a client quote. 1. Define the measured job Remove one bath and fit a shower in the same alcove, with a new base, wall finish, valve trim and screen allowance. Existing supply and drain positions remain. Measure the finished alcove on three sides, the wet-wall area and the drain location before selecting the base. Record the measurements and existing condition in the estimate before turning quantities into line items. The scope should make clear why this is a separate project from a broader renovation or maintenance quote. Measure for this job: Measure the finished alcove on three sides, the wet-wall area and the drain location before selecting the base. Put that measured basis beside the relevant PDF lines so area, fitted length and product purchase quantities stay distinct. 2. Build a product and labour schedule Keep the shower base, screen and finish tile as named allowances until the products are selected. This example has 7 distinct lines, including dust protection, bath and surround removal, shower base allowance. Use actual supplier prices and labour inputs for a customer job; the displayed amounts are fictional document inputs. Choose before pricing: Keep the shower base, screen and finish tile as named allowances until the products are selected. The fixture separates dust protection, bath and surround removal and shower base allowance rather than hiding all work in one figure. 3. Sequence the work and handoffs Confirm water shutoff, demolition, waterproofing inspection and curing time before promising a handoff date. Show which task depends on access, a selected product or another trade. If that dependency is still open, label the price preliminary and identify the information needed before a firm quote. Plan the handoffs: Confirm water shutoff, demolition, waterproofing inspection and curing time before promising a handoff date. Note which stage needs access, a selected product or another trade before the next stage can be priced confidently. 4. Set a change boundary Rot behind the surround or a drain that cannot align with the chosen base changes the work. The example excludes bathroom layout change, concealed structural repair or whole-room repainting. Record the discovery, agree the revised work and update the estimate before adding it to the job. Change trigger: Rot behind the surround or a drain that cannot align with the chosen base changes the work. Record the revised task and quantity before it changes the amount your client sees. Review the Australian job Verify the existing water and waste connections, access and selected fittings on site. Assign any specialist work and check approval requirements that apply to the actual address. The wet-wall preparation and waterproofing line uses 6.97 m². Keep the site measurement and supplier's selling unit together; a material purchase allowance can differ from installed coverage. The amounts are fictional AUD inputs, not current prices for Sydney, New South Wales or another location. Worked project calculation The paired PDF has 7 cost lines. For example, Shower base allowance is 1 each × A$965.20 = A$965.20; Wet-wall preparation and waterproofing is 6.97 m² × A$246.00 = A$1,714.62. Each amount comes from the stated quantity and unit rate, so you can trace the arithmetic back to the job scope. Bath to shower conversion example — AUD, fictional inputs Work item | Quantity | Unit rate | Amount | Dust protection | 1 job | A$209.55 | A$209.55 | Bath and surround removal | 1 job | A$533.40 | A$533.40 | Shower base allowance | 1 each | A$965.20 | A$965.20 | Wet-wall preparation and waterproofing | 6.97 m² | A$246.00 | A$1,714.62 | Wall finish installation | 6.97 m² | A$328.00 | A$2,286.16 | Valve trim and screen allowance | 1 set | A$1,244.60 | A$1,244.60 | Disposal and final seal | 1 job | A$241.30 | A$241.30 | Illustrative total | A$7,194.83 | Adding every exact-cent line gives A$7,194.83 . The PDF uses a 0% tax input only to make its fictional arithmetic visible. Confirm the GST treatment that applies to the actual job and set your own markup before sharing a client quote. A fictional rate is a document input, not a market quote or a recommended selling price. Scope and pricing boundaries Remove one bath and fit a shower in the same alcove, with a new base, wall finish, valve trim and screen allowance. Existing supply and drain positions remain. Outside this example: No bathroom layout change, concealed structural repair or whole-room repainting. Separate product allowances, supply, installation, disposal and any specialist work where the actual project needs them. If access or a hidden condition changes, document the affected scope and agree a revised price instead of silently extending the base amount. Before you send the estimate - Measure the finished alcove on three sides, the wet-wall area and the drain location before selecting the base. - Keep the shower base, screen and finish tile as named allowances until the products are selected. - Confirm water shutoff, demolition, waterproofing inspection and curing time before promising a handoff date. - Rot behind the surround or a drain that cannot align with the chosen base changes the work. Check business and client details, address, dates, scope, units, line amounts and PDF notes. The bath to shower conversion PDF example (https://quicklyestimates.com/en-au/samples/bathtub-to-shower-conversion-estimate/) shows how this fictional project is presented. Its short PDF note is not a substitute for the detailed exclusions above. Questions about this estimate Which quantity controls this bath to shower conversion estimate? Measure the finished alcove on three sides, the wet-wall area and the drain location before selecting the base. When should this bath to shower conversion quote be revised? Rot behind the surround or a drain that cannot align with the chosen base changes the work. No bathroom layout change, concealed structural repair or whole-room repainting. (https://quicklyestimates.com/en-au/samples/bathtub-to-shower-conversion-estimate/) First page of the fictional bath to shower conversion PDF estimate · View the matching example (https://quicklyestimates.com/en-au/samples/bathtub-to-shower-conversion-estimate/) TURN THE SCOPE INTO AN ITEMISED PDF Make your own bath to shower conversion estimate. Describe the actual job in Estimates on iPhone or Android or use AI assistance to start a draft. Check every measurement, quantity, rate, allowance, client detail and note before exporting your PDF. Some app features may require an in-app purchase. Create a quote ↗ (https://quicklyestimates.com/en-au/download/)Open the matching PDF example → (https://quicklyestimates.com/en-au/samples/bathtub-to-shower-conversion-estimate/) Related Australian estimating resources - Matching itemised example (https://quicklyestimates.com/en-au/samples/bathtub-to-shower-conversion-estimate/) - Bathroom vanity unit replacement estimate example (https://quicklyestimates.com/en-au/samples/bathroom-vanity-replacement-estimate/) - How to create a clear tradie quote (https://quicklyestimates.com/en-au/guides/create-a-tradie-quote/) Get the app: https://quicklyestimates.com/en-au/download/ App Store (iPhone): https://apps.apple.com/app/id6740389403 Google Play (Android): https://play.google.com/store/apps/details?id=com.uzel.contractorplus