EXAMPLE AT A GLANCE
This fictional Winnipeg, Manitoba interconnected smoke alarm installation example contains 7 itemized costs totaling C$2,720.00 before tax or markup. The app-exported PDF uses the exact quantities and CAD rates shown in the table, with scope limits explained below.
Project scope: Four alarm positions
Install four selected interconnected smoke alarms at agreed positions using suitable existing power or approved selected equipment.
The fictional project is set in Winnipeg, Manitoba. Cedar & Beam Builders and Jordan Taylor are example names, not a contractor and client case study. The matching guide explains how measurement, product selection and site conditions affect the estimate.
- Location
- Winnipeg, Manitoba
- Prepared by
- Cedar & Beam Builders · fictional business
- Prepared for
- Jordan Taylor · fictional client
- Issued / valid through
- September 25 / October 25, 2026
The 7 CAD cost lines
The table uses the exact items, quantities and unit rates in the app-exported PDF. Multiply each quantity by its rate to check the amount. These chosen figures demonstrate the document; they are not surveyed prices or suggested rates for Winnipeg, Manitoba.
| Work item | Quantity | Unit rate | Amount |
|---|---|---|---|
| Position survey and plan | 1 job | C$285.00 | C$285.00 |
| Alarm unit allowance | 4 each | C$130.00 | C$520.00 |
| Bases and connection parts | 1 set | C$245.00 | C$245.00 |
| Cable routing allowance | 1 job | C$430.00 | C$430.00 |
| Alarm fitting labour | 4 each | C$195.00 | C$780.00 |
| Interconnection test | 1 job | C$325.00 | C$325.00 |
| Handoff labels and cleanup | 1 job | C$135.00 | C$135.00 |
| Illustrative subtotal | C$2,720.00 | ||
Check the arithmetic
- Alarm unit allowance: 4 each × C$130.00 = C$520.00.
- Bases and connection parts: 1 set × C$245.00 = C$245.00.
The rounded line amounts add to C$2,720.00. The PDF's tax field is 0%, so its illustrated total stays C$2,720.00 before any markup. The sample shows 0% tax only to make the arithmetic visible. Determine any applicable GST, HST or PST and markup for the actual work before sharing a quote.
Measurement to verify: Count rooms and alarm positions, record ceiling construction and interconnection route. Product decision: Identify alarm units, bases and interconnection components separately.
Count the actual units, site visits and selected products separately. A count in this example is a document input, not a substitute for inspecting the real property.
Assumptions and exclusions
Confirm the required local design with a qualified installer before setting the positions.
Outside this example: No whole-building fire-system design, panel replacement or guarantee of regulatory compliance without review.
A missing circuit or inaccessible route changes installation method. Have the actual supply route, mounting and testing reviewed by the qualified person doing the work. Confirm any approval or inspection requirements for the project address before issuing a final price. Confirm a change and update the estimate before adding work that was not in the base scope.
Download the actual app PDF
The PDF was exported from Estimates for this fictional Canadian job. It carries a concise version of the project scope, plus the same customer, cost lines, CAD amounts and total used here. Its note covers the fictional tax setting and the brief's full exclusion sentence; the article records additional assumptions that do not fit in that PDF note.
Build the next estimate from your own inputs
- Measure the actual site and describe the work boundary in plain language.
- Confirm the selected products, access and handoff responsibilities with the client.
- Replace every fictional rate with your own labour, supplier and subcontractor figures.
- Check the relevant GST, HST or PST treatment and markup for the job without copying this sample's zero entry.
- Preview each PDF page, total and exclusion note before sharing.
- Count rooms and alarm positions, record ceiling construction and interconnection route.
- Identify alarm units, bases and interconnection components separately.
- Confirm the required local design with a qualified installer before setting the positions.
- A missing circuit or inaccessible route changes installation method.
Questions about this estimate
Which quantity controls this interconnected smoke alarm installation estimate?
Count rooms and alarm positions, record ceiling construction and interconnection route.
When should this interconnected smoke alarm installation quote be revised?
A missing circuit or inaccessible route changes installation method. No whole-building fire-system design, panel replacement or guarantee of regulatory compliance without review.