EXAMPLE AT A GLANCE
This fictional Exeter utility sink installation project has 7 itemised lines and an illustrative £1,348.00 total. The app-exported PDF, first-page preview, measurement basis, scope boundaries and matching UK estimating guide let you inspect every quantity and rate.
What this example covers
This fictional job is set in Exeter and concerns one new utility-room sink. Install one selected utility sink near existing suitable water and drain services, with tap, trap and wall or floor support. The estimate is a bounded document: the customer should be able to compare the described work with its measured lines, product allowances and exclusions. The matching UK guide explains how to prepare those inputs.
- Prepared by
- Cedar & Beam Builders · fictional business
- Prepared for
- Jordan Taylor · fictional customer
- Example location
- Exeter, UK
- Issued / valid through
- 25 September 2026 / 25 October 2026
Itemised utility sink installation example
These 7 lines reproduce the app-exported PDF exactly. The largest is Sink product allowance at £312.00; this is one fictional component, not a typical price. Read each quantity with its unit: area, length, time, count and lump sum describe different work and must not be interchanged.
| Work item | Quantity | Unit rate | Amount |
|---|---|---|---|
| Site measurement and protection | 1 lump sum | £108.00 | £108.00 |
| Sink product allowance | 1 each | £312.00 | £312.00 |
| Tap allowance | 1 each | £144.00 | £144.00 |
| Waste and supply fittings | 1 lump sum | £176.00 | £176.00 |
| Support and mounting | 1 lump sum | £224.00 | £224.00 |
| Water and drain connection | 1 lump sum | £288.00 | £288.00 |
| Leak check and clean-up | 1 lump sum | £96.00 | £96.00 |
| Illustrative total | £1,348.00 | ||
The table separates the named product or material allowances from labour and site tasks wherever the scope needs that distinction. Before replacing a rate, check whether the product allowance includes delivery, waste, fixings and the selected specification.
How the total is calculated
Site measurement and protection is 1 lump sum × £108.00 = £108.00. Sink product allowance is 1 each × £312.00 = £312.00. The other lines follow the same calculation and sum to £1,348.00. Each fixture line lands on an exact penny, so the native PDF total equals the sum of the displayed line amounts.
Measurement to check: Measure sink footprint, service route, fixing support and working clearance. Selection to check: Separate sink, tap and connection materials from fit-out labour. The 0% tax field and zero markup are example document inputs, not an instruction for a live quote. Decide the correct settings for your own business and job.
Assumptions and exclusions
Confirm drain fall and shutoff before fixing the sink.
Outside this stated scope: No new room drainage, cabinet fitout or floor repair.
Hidden pipework or weak wall support can change the mounting method. A changed condition should lead to a newly measured quantity, explicit revised allowance or separately agreed task. Keep the customer informed of which figure changed and why before producing another PDF.
Download the app PDF
The document was exported from Estimates using the fictional business, client, dates, short PDF scope, notes and cost lines above. Its first page appears below. Download the complete PDF to inspect every entry and its presentation; no listed rate is a current Exeter market claim.
Make an estimate for your own job
- Write the actual work boundary and exclusions. Use this measurement basis: Measure sink footprint, service route, fixing support and working clearance.
- Confirm the selected products and access conditions. Record this selection decision: Separate sink, tap and connection materials from fit-out labour.
- Replace every fictional product, labour and subcontractor rate with your own evidence.
- Check line extensions, total, tax and markup settings, customer details and validity date.
- Preview every PDF page before sharing the estimate with the customer.
- Measure sink footprint, service route, fixing support and working clearance.
- Separate sink, tap and connection materials from fit-out labour.
- Confirm drain fall and shutoff before fixing the sink.
- Hidden pipework or weak wall support can change the mounting method.
Read the matching estimating guide for the project-specific measurement and work sequence.
Questions about this job
Which quantity controls this utility sink installation estimate?
Measure sink footprint, service route, fixing support and working clearance.
When should this utility sink installation quote be revised?
Hidden pipework or weak wall support can change the mounting method. No new room drainage, cabinet fitout or floor repair.
MAKE THE EXAMPLE YOUR OWN
Build a utility sink installation estimate
Use Estimates on iPhone or Android to enter your measured scope and line items. Review the result carefully and export a PDF for the actual job.