Painting & surfaces · Edinburgh · GBP

Kitchen cabinet painting estimate example in Edinburgh: itemised PDF

Download a fictional UK kitchen cabinet painting estimate PDF with 7 itemised lines totalling £4,380.80. Check the quantities, GBP rates, scope and exclusions.

EXAMPLE AT A GLANCE

This fictional Edinburgh kitchen cabinet painting project has 7 itemised lines and an illustrative £4,380.80 total. The app-exported PDF, first-page preview, measurement basis, scope boundaries and matching UK estimating guide let you inspect every quantity and rate.

What this example covers

This fictional job is set in Edinburgh and concerns eighteen doors and six drawers. Prepare and coat 18 kitchen cabinet doors and six drawer fronts, with frames finished in place. Existing boxes remain. The estimate is a bounded document: the customer should be able to compare the described work with its measured lines, product allowances and exclusions. The matching UK guide explains how to prepare those inputs.

Prepared by
Cedar & Beam Builders · fictional business
Prepared for
Jordan Taylor · fictional customer
Example location
Edinburgh, UK
Issued / valid through
25 September 2026 / 25 October 2026

Itemised kitchen cabinet painting example

These 7 lines reproduce the app-exported PDF exactly. The largest is Coat doors and drawers at £1,824.00; this is one fictional component, not a typical price. Read each quantity with its unit: area, length, time, count and lump sum describe different work and must not be interchanged.

Kitchen cabinet painting in Edinburgh — GBP, fictional inputs
Work itemQuantityUnit rateAmount
Masking and door schedule1 lump sum£208.00£208.00
Remove and label fronts24 each£14.40£345.60
Degrease and sand16 hours£38.40£614.40
Primer and coating allowance1 lump sum£416.00£416.00
Coat doors and drawers24 each£76.00£1,824.00
Frame coating in place1 lump sum£512.00£512.00
Rehang and adjustment24 each£19.20£460.80
Illustrative total£4,380.80

The table separates the named product or material allowances from labour and site tasks wherever the scope needs that distinction. Before replacing a rate, check whether the product allowance includes delivery, waste, fixings and the selected specification.

How the total is calculated

Remove and label fronts is 24 each × £14.40 = £345.60. Degrease and sand is 16 hours × £38.40 = £614.40. The other lines follow the same calculation and sum to £4,380.80. Each fixture line lands on an exact penny, so the native PDF total equals the sum of the displayed line amounts.

Measurement to check: Count fronts, exposed frame area and removable hardware; record the existing finish for adhesion preparation. Selection to check: Specify coating, colour, primer and whether new hardware is included as separate choices. The 0% tax field and zero markup are example document inputs, not an instruction for a live quote. Decide the correct settings for your own business and job.

Assumptions and exclusions

Label each front before removal and plan off-site or staged curing before rehang.

Outside this stated scope: No cabinet replacement, internal box painting or worktop changes.

Peeling laminate or oil contamination may require more preparation than the base allowance. A changed condition should lead to a newly measured quantity, explicit revised allowance or separately agreed task. Keep the customer informed of which figure changed and why before producing another PDF.

Download the app PDF

The document was exported from Estimates using the fictional business, client, dates, short PDF scope, notes and cost lines above. Its first page appears below. Download the complete PDF to inspect every entry and its presentation; no listed rate is a current Edinburgh market claim.

First page of the fictional kitchen cabinet painting estimate PDF

Make an estimate for your own job

  1. Write the actual work boundary and exclusions. Use this measurement basis: Count fronts, exposed frame area and removable hardware; record the existing finish for adhesion preparation.
  2. Confirm the selected products and access conditions. Record this selection decision: Specify coating, colour, primer and whether new hardware is included as separate choices.
  3. Replace every fictional product, labour and subcontractor rate with your own evidence.
  4. Check line extensions, total, tax and markup settings, customer details and validity date.
  5. Preview every PDF page before sharing the estimate with the customer.
  • Count fronts, exposed frame area and removable hardware; record the existing finish for adhesion preparation.
  • Specify coating, colour, primer and whether new hardware is included as separate choices.
  • Label each front before removal and plan off-site or staged curing before rehang.
  • Peeling laminate or oil contamination may require more preparation than the base allowance.

Read the matching estimating guide for the project-specific measurement and work sequence.

Questions about this job

Which quantity controls this kitchen cabinet painting estimate?

Count fronts, exposed frame area and removable hardware; record the existing finish for adhesion preparation.

When should this kitchen cabinet painting quote be revised?

Peeling laminate or oil contamination may require more preparation than the base allowance. No cabinet replacement, internal box painting or worktop changes.

MAKE THE EXAMPLE YOUR OWN

Build a kitchen cabinet painting estimate

Use Estimates on iPhone or Android to enter your measured scope and line items. Review the result carefully and export a PDF for the actual job.

Plain-text version · Browse all samples

Less paperwork. More time for the job.

Make your next estimate on iPhone or Android, then review it before sharing.

Download on the App StoreGet it on Google Play