EXAMPLE AT A GLANCE
An accessible entry ramp installation example for one short private entry ramp contains 7 itemized lines totaling $9,900.00 before tax or markup. The actual app PDF, measurement basis, project boundaries and a matching how-to guide are available here; every rate is fictional.
What this example covers
Build a short ramp at a private entry to a site-reviewed design with non-slip surface, edge protection and handrail allowance.
Use this example to see a complete document for one short private entry ramp. The brief is tied to Cincinnati, Ohio for a plausible project setting; the amounts are fictional input values and do not represent local market prices. The estimating guide explains the decisions behind these lines.
- Prepared by
- Cedar & Beam Builders Β· fictional business
- Prepared for
- Jordan Taylor Β· fictional customer
- Example project
- One short private entry ramp
- Issued / valid through
- September 25, 2026 / October 25, 2026
Itemized accessible entry ramp installation example
These are the same quantities and unit prices used by the downloadable app PDF. A cost line can represent measured work, a selected product allowance or a distinct site task. Check which interpretation applies before replacing any amount.
| Work item | Quantity | Unit price | Amount |
|---|---|---|---|
| Entry survey and design allowance | 1 job | $490.00 | $490.00 |
| Site preparation | 1 job | $390.00 | $390.00 |
| Frame or base material allowance | 1 job | $1,450.00 | $1,450.00 |
| Ramp construction labor | 120 sq. ft. | $28.00 | $3,360.00 |
| Non-slip surface allowance | 130 sq. ft. | $12.00 | $1,560.00 |
| Handrail and edge allowance | 36 linear ft. | $65.00 | $2,340.00 |
| Level check and cleanup | 1 job | $310.00 | $310.00 |
| Subtotal / example total | $9,900.00 | ||
How the subtotal is calculated
The example line for ramp construction labor is 120 sq. ft. Γ $28.00 = $3,360.00. This line is one part of the complete 7-item estimate and uses a fictional unit rate.
The document sums the rounded line amounts to $9,900.00. Tax and markup are not included; a zero tax field in a sample document does not mean a real project is tax-exempt. Confirm the actual treatment for the job you are quoting.
Measurement to verify: Survey rise, available run, landings, door swing and drainage; slope must follow locally applicable design. Selection to verify: Separate structural material, surface and rail allowances.
Assumptions and exclusions
Obtain the required design and permissions before construction; check levels at each stage.
Outside the stated scope: No accessibility certification, public sidewalk work or structural foundation redesign.
Insufficient available run or weak landing support changes the design. If the scope changes after a client reviews the estimate, update the relevant quantities, allowances and written exclusions before sharing a revised PDF.
Download the actual app PDF
The downloadable document was exported from Estimates using the fictional business, client, scope and cost lines shown above. The preview is its first page. Review the full PDF before using its layout or wording as a reference for your own estimate.
Build your own version
- Write the actual job boundary and measured quantities. Measurement basis to check: Survey rise, available run, landings, door swing and drainage; slope must follow locally applicable design.
- Confirm products, access and handoff responsibilities. Selection decision to record: Separate structural material, surface and rail allowances.
- Replace every fictional rate with your own supplier, labor and subcontractor inputs.
- Add business and client details, set the appropriate tax and markup, then preview all PDF pages.
- Share the estimate with its exclusions and a clear validity date.
- Survey rise, available run, landings, door swing and drainage; slope must follow locally applicable design.
- Separate structural material, surface and rail allowances.
- Obtain the required design and permissions before construction; check levels at each stage.
- Insufficient available run or weak landing support changes the design.
Questions about this estimate
Which quantity controls this accessible entry ramp installation estimate?
Survey rise, available run, landings, door swing and drainage; slope must follow locally applicable design.
When should this accessible entry ramp installation quote be revised?
Insufficient available run or weak landing support changes the design. No accessibility certification, public sidewalk work or structural foundation redesign.