EXAMPLE AT A GLANCE
This interior demolition estimate contains 6 line items totaling $1,850.00. It includes an app-exported PDF, a visible calculation table and explicit exclusions. All prices are fictional and exclude tax and markup.
The nonstructural finish removal scope
Remove 300 square feet of floor finish, 200 square feet of wall board and 12 linear feet of cabinets in a cleared work area. Include protection, a scoped debris-handling allowance and cleanup. No structural or service-system work.
- Prepared by
- Cedar & Beam Builders · fictional business
- Prepared for
- Jordan Taylor · fictional customer
- Example location
- Columbia, South Carolina
- Issued / valid through
- September 21 / October 21, 2026
Itemized interior demolition estimate
The table below uses the same quantities and unit prices as the downloadable PDF. Amounts are in US dollars; the location provides context and does not make these local market rates.
| Work item | Quantity | Unit price | Amount |
|---|---|---|---|
| Work-area protection and setup | 1 job | $275.00 | $275.00 |
| Floor finish removal | 300 sq. ft. | $1.25 | $375.00 |
| Specified wall-board removal | 200 sq. ft. | $1.50 | $300.00 |
| Cabinet removal | 12 linear ft. | $25.00 | $300.00 |
| Debris handling and disposal allowance | 1 job | $450.00 | $450.00 |
| Final work-area cleanup | 1 job | $150.00 | $150.00 |
| Subtotal / example total | $1,850.00 | ||
Tax and markup: not included. Determine and apply the appropriate values for your own job. A zero tax entry in this example does not mean the work is tax-exempt.
How to read the quantities
Floor removal is 300 sq. ft. × $1.25 = $375. Wall-board removal is 200 × $1.50 = $300. The combined $675 does not include the separately stated debris-handling allowance.
What the example includes—and leaves out
Identify any assessment, service isolation or material testing required for the actual job. Do not assume concealed conditions are safe or included. This example prices defined finish removal only and is not a procedure for carrying out demolition.
Outside this scope: No structural demolition, utility disconnection, hazardous-material abatement, concealed-condition repairs or reconstruction.
Keep unresolved selections and site conditions visible. If a measurement, material choice or repair requirement changes, revise the relevant quantity or allowance and share the updated estimate before proceeding with the added work.
Download the actual app PDF
This is a completed example, not a blank fillable form. It was exported from Estimates using the project data on this page. The business logo, client details, scope, line amounts, total and notes come from the app’s document renderer.
Use the example for your next job
- Replace the scope and location with your actual project.
- Use the checklist below to collect missing selections and measurements.
- Replace every example rate with your own supplier and labor inputs.
- Add your business logo, client details, tax, markup and validity date.
- Preview every PDF page and review the total before sharing.
- Identify retained and removed components.
- Confirm prerequisite assessments and service arrangements.
- Record debris access and disposal assumptions.
- Define cleanup and reconstruction boundaries.

Common questions
Does a demolition estimate include rebuilding?
Not unless rebuilding is explicitly listed. Separate removal, cleanup and reconstruction so the customer understands the condition left at the end of each scope.
Why show debris handling separately?
Removal effort and disposal arrangements can change independently. A defined handling line makes access constraints and provider charges easier to review.
TAKE THE NEXT JOB FROM SCOPE TO PDF
Make your own interior demolition estimate.
Use Estimates on iPhone or Android to draft a scope with AI assistance or enter your own items. Review quantities and rates, add your business logo, and export a PDF. Example files are free to view; app features may require an in-app purchase.