EXAMPLE AT A GLANCE
A garden masonry wall rebuild example for one damaged boundary-wall section contains 7 itemized lines totaling $5,850.00 before tax or markup. The actual app PDF, measurement basis, project boundaries and a matching how-to guide are available here; every rate is fictional.
What this example covers
Take down and rebuild a short damaged garden masonry wall section on a suitable existing foundation, with matching units and coping allowance.
Use this example to see a complete document for one damaged boundary-wall section. The brief is tied to Indianapolis, Indiana for a plausible project setting; the amounts are fictional input values and do not represent local market prices. The estimating guide explains the decisions behind these lines.
- Prepared by
- Cedar & Beam Builders Β· fictional business
- Prepared for
- Jordan Taylor Β· fictional customer
- Example project
- One damaged boundary-wall section
- Issued / valid through
- September 25, 2026 / October 25, 2026
Itemized garden masonry wall rebuild example
These are the same quantities and unit prices used by the downloadable app PDF. A cost line can represent measured work, a selected product allowance or a distinct site task. Check which interpretation applies before replacing any amount.
| Work item | Quantity | Unit price | Amount |
|---|---|---|---|
| Site survey and protection | 1 job | $210.00 | $210.00 |
| Careful wall dismantling | 65 sq. ft. | $14.00 | $910.00 |
| Waste handling | 1 job | $280.00 | $280.00 |
| Matching units allowance | 70 sq. ft. | $26.00 | $1,820.00 |
| Mortar and tie allowance | 1 job | $240.00 | $240.00 |
| Wall rebuilding labor | 65 sq. ft. | $32.00 | $2,080.00 |
| Coping and cleanup | 1 job | $310.00 | $310.00 |
| Subtotal / example total | $5,850.00 | ||
How the subtotal is calculated
The example line for careful wall dismantling is 65 sq. ft. Γ $14.00 = $910.00. This line is one part of the complete 7-item estimate and uses a fictional unit rate.
The document sums the rounded line amounts to $5,850.00. Tax and markup are not included; a zero tax field in a sample document does not mean a real project is tax-exempt. Confirm the actual treatment for the job you are quoting.
Measurement to verify: Measure wall length, height, thickness and salvageable units; inspect the existing footing. Selection to verify: Identify new matching units, mortar and coping as product allowances.
Assumptions and exclusions
Record protection of neighbouring property and sequence careful dismantling before rebuilding.
Outside the stated scope: No new footing, structural design or work on uninspected adjacent wall.
A failed footing or unstable adjoining wall changes the construction scope. If the scope changes after a client reviews the estimate, update the relevant quantities, allowances and written exclusions before sharing a revised PDF.
Download the actual app PDF
The downloadable document was exported from Estimates using the fictional business, client, scope and cost lines shown above. The preview is its first page. Review the full PDF before using its layout or wording as a reference for your own estimate.
Build your own version
- Write the actual job boundary and measured quantities. Measurement basis to check: Measure wall length, height, thickness and salvageable units; inspect the existing footing.
- Confirm products, access and handoff responsibilities. Selection decision to record: Identify new matching units, mortar and coping as product allowances.
- Replace every fictional rate with your own supplier, labor and subcontractor inputs.
- Add business and client details, set the appropriate tax and markup, then preview all PDF pages.
- Share the estimate with its exclusions and a clear validity date.
- Measure wall length, height, thickness and salvageable units; inspect the existing footing.
- Identify new matching units, mortar and coping as product allowances.
- Record protection of neighbouring property and sequence careful dismantling before rebuilding.
- A failed footing or unstable adjoining wall changes the construction scope.
Questions about this estimate
Which quantity controls this garden masonry wall rebuild estimate?
Measure wall length, height, thickness and salvageable units; inspect the existing footing.
When should this garden masonry wall rebuild quote be revised?
A failed footing or unstable adjoining wall changes the construction scope. No new footing, structural design or work on uninspected adjacent wall.
TURN THIS EXAMPLE INTO YOUR OWN ESTIMATE
Build a garden masonry wall rebuild estimate for your project
Use Estimates on iPhone or Android to draft a scope with AI assistance or enter each line yourself. Review quantities, rates, exclusions, and client details before exporting a PDF. The example is free to inspect; some app features may require an in-app purchase.