EXAMPLE AT A GLANCE
This fictional gutter replacement quote for Sydney, New South Wales has 7 itemised lines totalling A$2,324.28. Review the exact metric quantities and scope, then open the matching app-exported PDF. The 0% tax entry is only an example input.
The 42.67 m gutter replacement scope
Replace 42.67 m of accessible gutters and 9.75 m of downpipes on a single-storey home. Include removal, material allowances, installation, four power point assemblies and cleanup. Existing fascia assumed suitable.
This is an original fictional job set in Sydney, New South Wales. The location gives the example a recognisable setting; the rates are made-up inputs and do not describe local prices. Use the matching estimating guide to check what should be measured, selected or excluded on a real job.
- Prepared by
- Harbour & Gum Projects · fictional business
- Prepared for
- Alex Morgan · fictional customer
- Example location
- Sydney, New South Wales
- Issued / valid through
- 25 September 2026 / 25 October 2026
Itemised gutter replacement example
Each amount is its quantity multiplied by its AUD unit rate, rounded to cents. These 7 entries match the fixture used to make the PDF. Metric surface and length units describe the priced work, not a conversion rule for another property.
| Work item | Quantity | Unit rate | Amount |
|---|---|---|---|
| Existing gutter removal | 42.67 m | A$6.00 | A$256.02 |
| Gutter material allowance | 42.67 m | A$18.00 | A$768.06 |
| Downpipe material allowance | 9.75 m | A$13.80 | A$134.55 |
| Gutter installation labour | 42.67 m | A$16.00 | A$682.72 |
| Downpipe installation labour | 9.75 m | A$11.48 | A$111.93 |
| Power points and connection hardware | 4 sets | A$49.00 | A$196.00 |
| Disposal and cleanup | 1 job | A$175.00 | A$175.00 |
| Subtotal / example total | A$2,324.28 | ||
Calculation check: 42.67 m × A$6.00 = A$256.02; 42.67 m × A$18.00 = A$768.06. The demonstration tax field is 0%, so the displayed total stays A$2,324.28. Determine tax and markup for your own work instead of using this input as guidance.
Assumptions and scope boundaries
New gutters depend on the condition of the supporting surface. This example assumes suitable fascia. If repairs are visible or likely, inspect and price them separately rather than allowing a replacement gutter line to imply carpentry work.
Outside this example: No fascia replacement, multi-storey access, underground drainage, gutter guards or drainage-system design.
Selections, access or concealed conditions that differ from this scope require a revised quantity, allowance or separate line. The example deliberately separates them so the client can see what has and has not been priced.
Open the app-exported PDF
The PDF is a completed example exported from Estimates using this job data, fictional parties and the line amounts above. Read all pages to check notes as well as the total. The preview is the first page.
Adapt this example to your next job
- Replace the example location and project description with the actual site and client's requested result.
- Measure the work in the units shown, revising each quantity and product allowance to suit your plans and site inspection.
- Obtain your own supplier and labour inputs, then check access, protection, disposal and any specialist trade boundaries.
- Record exclusions and choices that remain open; review markup and tax for the actual quote.
- Preview every page of the PDF and check the item totals before sharing it.
- Count runs, corners, power points and downpipes.
- Inspect the fascia assumption.
- State where discharge work ends.
- Separate optional accessories and drainage connections.
Common questions about gutter replacement
Should downpipes be included in gutter length?
Measure and label them separately. Horizontal gutter runs and vertical downpipes have different quantities and may have different material and labour rates.
Are gutter guards included automatically?
No. List them as included work or a separate option, with the selected product and quantity.
FROM SCOPE TO PDF
Make your own gutter replacement estimate.
Describe the actual job in Estimates on iPhone or Android, then review every quantity, rate and scope note. Add your business and client details, check the document and share an itemised PDF. Example amounts are fictional, and some app features may require an in-app purchase.